Council has an ongoing program of capital works and upgrades to buildings, parks, playgrounds and roads across the Federation Council Region.

The following activities were undertaken within the month of June 2021 by Federation Council’s Works teams:

  • Fixing Local Roads Program - Vegetation Safety Progra:  completed (contractor in conjunction with Council).
  • FLR Program - Traffic Facilities - Continue audit of signs & guideposts for upgrade/replacement in urban streets and rural roads throughout Federation Council. Commence replacement program of signs & guideposts. Completion of upgrade of Regulatory town speed limit signs from “A” size to “B” size, (50, 60, 80, 100 km/h), Howlong, Urana, Boree Creek.
  • Church Street water main 300mm Works - completed.
  • Corowa – Mulwala Cycleway Works on hold due to wet weather.
  • LRCI Grant - Gravel Roads Maintenance Carrols lane, Woolshed Road, Lavis Road, Glencoe Road, Glenara Road, Lilydale Road, Morningside Road, Piggins Road, Felton Road, Mahonga Lane.
  • LRCI grant – Hume Street Mulwala Kerb & Gutter Replacement Stage two - Works 90% complete, sealing works will be undertaken when weather conditions are more favourable.
  • Spring Drive/Stuckeys Road (MR 314 segment 230) - Removal of redundant culvert and drainage works – in conjunction with Transport for NSW.